Inner NE Sewer Extension Construction Update: September 9, 2014

As part of the City of Portland’s effort to provide properties with sewer connections that comply with city code, Environmental Services continues construction on the Inner NE Sewer Extension project. This project will also help protect public health, property, and the environment by increasing the capacity of the public sewer system, reducing the potential for basement backups, and reducing the likelihood of emergency maintenance work in the future.

 

A project map is available at www.portlandoregon.gov/bes/InnerNE.

 

DEVELOPMENTS OF NOTE

Paving on NE 8th Avenue (Prescott to Going) begins tomorrow

  • Crews are scheduled to begin paving the south half of NE 8th Avenue between NE Prescott and Going streets tomorrow. Crews are scheduled to grind down the existing roadway from curb to curb and perform additional preparations on Wednesday and Thursday.  Final paving is scheduled for Friday.
  • Please observe NO PARKING signs.

 

Periodic traffic delays on NE Prescott will continue

  • From 9:00 a.m. to 3:00 p.m. Monday through Friday, motorists and cyclists should expect delays on NE Prescott Street between NE 6th and 10th avenues.  Crews will be installing new main public sewer pipes and constructing several manholes. The work will be taking place in phases, and some phases will require flaggers to direct traffic around the work zone.

 

CONSTRUCTION SCHEDULE

Below is the estimated Inner NE Sewer Extension construction schedule for the rest of this week and next week. Please be aware that this schedule is subject to change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials. There may be periods of inactivity between construction phases.

 

The rest of this week

  • NE 7th Avenue (Prescott to Going) – trench preparation and paving
  • NE 8th Avenue (Prescott to Going) – street preparation and paving
  • NE 10th Avenue (Prescott to Going) – main public sewer pipe, manhole, and lateral branch construction
  • NE 10th Avenue (Going to Wygant) – main public sewer pipe, manhole, and lateral branch construction

 

Week of September 15

  • NE 9th Avenue (Wygant to Humboldt) – main public sewer pipe, manhole, and lateral branch construction
  • NE 10th Avenue (Going to Wygant) – lateral branch construction

 

WHAT TO EXPECT DURING CONSTRUCTION

  • Construction creates noise, vibration and dust and disrupts normal neighborhood activity.
  • Typical work hours are 7:00 a.m. to 6:00 p.m. Monday through Friday, but the contractor may schedule work during the same hours on Saturdays.
  • Please stay clear of all construction activities and keep children, pets and vehicles out of construction areas.
  • Traffic control signs are in place. The contractor maintains local access, but you should expect delays.
  • On-street parking in or near the work area may be limited. Please observe no parking signs.
  • Equipment and materials may be stored on nearby streets overnight.
  • A city inspector is on-site during work hours and may be able to assist you with construction concerns. Inspectors will be wearing a hard hat and a safety vest with “City of Portland” on the back.

 

FOR MORE INFORMATION

Go to www.portlandoregon.gov/bes/InnerNEor email me at Matthew.Gough@portlandoregon.gov.

 

Thank you for your cooperation during this project. Please let us know if you have concerns such as business operations, disability issues or medical or business deliveries. As always, we’ll strive to provide quick response to your concerns, minimal disruption of your residence or commercial business, and open and honest communication with you throughout the project.

 

Thank you,

 

Matt Gough

Community Outreach and Information

City of Portland Environmental Services

1120 SW 5th Ave, Room 1000

Portland, Oregon 97204

Phone: 503-823-5352 l Cell Phone: 503-823-6622

Email: Matthew.Gough@portlandoregon.gov